top of page

Deployments /1

LT Boardman OR: Port of Morrow Wastewater Lagoons

Wastewater-to-Baseload Power & Municipal Waterworks Plant

Phase 1: 300 MW / Phase 2: 500 MW / Phase 3: 600 MW

City of Boardman, at The Port of Morrow in Morrow County, Oregon USA

​

A multi-phase project of which the first 300 MW housing has been constructed on site. Shown below are designs for the plant's build-out.

LT 500MW WTE Plant Boardman
LT 500MW WTE Plant Boardman

PLANT CONSTRUCTION SITE PHOTOS

Located adjacent to The Port of Morrow, this project will be the first truly self-sustained regenerative power plant. It is a completely renewable system to convert waste into municipal water and energy.  The core structure has been constructed as seen in the photos at left.

Construction began in early 2020, and currently on-standby pending federal, state and local dynamics. In 2019, the last coal-fired power plant in the state of Oregon was demolished, creating an urgent need for this new Langenburg baseload power plant.

PLANT FEATURES

  • BANK 1 (existing housing built on site):  300 megawatts baseload/peak power;

  • BANK 2 (next housing to be built on site) :  200 megawatts baseload power;

  • 10 x 50 MW Langenburg-proprietary power units;

  • electrical load-following and 1-minute black start (without external hydraulic starter);

  • separation of pure water component from raw industrial liquid waste for municipal tap supply;

  • residual liquid waste concentrate conversion to non-carbon synthetic hydrogen-based fuel;

  • zero emissions from the turbines;

  • 100% waste conversion without any residual.

PLANT COMPONENT LINES

Typical Equipment Array LT-W2E Plant

<< langenburg components 
INTAKE CONVERTER > FUEL SYNTHESIZER > TURBINE > GENERATOR > CONVERTER 

substation components >>
VOLTAGE TRANSFORMER > CURRENT TRANSFORMER > BREAKER > POWER GRID

PLANT PHASE 1-3 SPECIFICATIONS 

Status
System Intake Fluid Consumption/MW
System Intake Fluid Type
Project Intake Fluid Type
Fuel Type 
Project Build-Phase Capacity
Turbine Type
Generator Type
Deployment Use
LT-50 MW Closed-Cycle GenSet Measure
Material Products

Construction on hold; first of 2 300 MW enclosures has been erected on site.
≈1.1 cubic meter/MW (configurable/variable by density & dissolved solids).
water, liquid, or material slurry (configurable).
Municipal and industrial wastewater sourced from treatment lagoons.
LT-Proprietary Synthetic NonCarbon Hydrogen-Based UltraFuel™ produced on-demand
Phase 1 = 300 MW / Phase 2 = 500 MW / Phase 3 = 600 MW.
Qty 6/10/12; 50 MW LT—Proprietary closed-cycle regenerative hydrodynamic.
Qty 6/10/12; 50 MW LT—Proprietary regenerative quantum-electrodynamic.
Wastewater conversion to robust baseload power transmission to consumer grid.
≈ 32’L  x 10’W  x 16‘H (as shown in 3D-model of plant in Port of Morrow, OR) / ≈50K lbs
Municipal water, LT UltraFuel™, baseload grid power, & oxygen water.

The liquid waste intake capacity target is 6-10 million gallons per day.  Over 95% of the water content is separated from the intake stream, then treated and purified as municipal tap supply water.  All remaining component byproducts from the intake are converted to non-carbon fuel used to operate an emission-free Langenburg-proprietary closed-cycle regenerative turbine.  Each of the turbines are connected to Langenburg-proprietary regenerative quantum-electrodynamic power generators collectively operating at 500 MW baseload capacity, with standby excess of 50-100 MW of peak capacity.  A major fraction of the plant’s capacity is also available for load-balancing.  The power will be supplied local industrial users including food production and online web service farms, as well as electrical power supply for the consumer grid.

PLANT ENTRANCE GATES BUILT BY LANGENBURG

As shown in the 3D model of the final plant build-out, two sets of heavy-duty entrance gates have been custom built by Langenburg.

LT Boardman WTE Plant – Entrance Gates
LT 500MW WTE Plant Boardman

The below 3D-ArchViz computer model shows the piping connection between the wastewater lagoon's pump-house, and the Langenburg waste-to-energy facility.  100% of the wastewater is converted to potable water and electrical grid power. The Langenburg conversion function replaces a conventional wastewater treatment plant. There is no temporal or chemical pre-treatment requirements for the wastewater to be converted in the Langenburg plant.

LT 500MW Waste-2-Energy Plant

PROJECT LOCATION

Deployments /2

LT Cordele GA:  Landfill & Recycling Center 

Beverage Wastewater-to-Baseload Power, Synthetic Fuel & Water

Phase 1: Water Separation / Phase 2: Waste Conversion to Fuel / Phase 3: Steam-Turbine Power

Synergy Solutions of Crisp County

Landfill / Mixed Solid Waste Recycling / Beverage Wastewater Recycling / Ethanol Distillery

A multi-phase project operating since 2019

LT Cordele GA Project.jpg

Show below-right, are the holding tanks in which the collected/mixed beverage wastewater is pre-treated by adding organisms to facilitate fermentation.  The facility has been using a distillery to take the volatile ethanol for collection, processing and sale to the petrochemical industry as a gasoline additive. 
  
The remaining liquid after fermentation, is routed into the Langenburg wastewater-to-energy system, where the pure water is separated from this intake. The remaining concentrate of dissolved solids are converted to non-carbon synthetic fuel that replaces the need to use Diesel, propane or natural gas to operate the ethanol distillery.

The below-left, is the Langenburg system housed in a truck box, which is currently installed and connected to the LT Georgia project at Synergy Solutions of Crisp County – a recycling facility that includes the processing of wastewater sourced from the beverage industry.

LT Cordele System Connection
Collected Beverage Waste Fermentation Tanks

Shown below, shows the ethanol distillers that is operated using the synthesized non-carbon LT UltraFuel™ – representing a free source of heat, that replaces the former usage of Diesel, natural gas and propane.

LT Coredele Equipment – Ethanol Distillers

Shown below, are the transparent view-ports that reveal fluid movement and stages of processing until the fermented mixed-beverage intake is converted to synthetic non-carbon LT UltraFuel™, and pure drinking-grade water.

LT Cordel SubComponents
LT Cordel SubComponents

Shown below, is a schematic flow diagram showing inputs, outputs and processing stages. In the upper-right corner, the only intake presented is mixed beverage wastewater that has been fermented in large holding tanks.

LT Georgia – Functional Diagram

Langenburg phase 1 retrofits

SEPARATE WATER FROM LIQUID INTAKE 

 

In phase-1, Langenburg system components are utilized to separate the pure-water component from re-brewed beverage waste for production of bottling-grade drinking water.  The Synergy facility collects expired and contaminated beverages, crushes the containers and recycles the packaging.  Volatile ethanol is heat-distilled from the heavier fraction of the re-brew before processing by Langenburg system components.

Langenburg phase 2 retrofits

CONVERT RESIDUAL WASTE CONCENTRATES TO FUEL

 

Phase-2 implements the Langenburg Core Tech Solution™ to produce non-carbon fuel by converting residual concentrates leftover after from the water separation process.  Langenburg proprietary fuel replaces Diesel as the heat source used by boilers, providing the heat source for a value-added distillation process without pollutive emissions.  Because the fuel is produced on-site, fuel delivery cost is eliminated.  Because the fuel is produced exclusively from waste, former use and cost of Diesel becomes obsolete.   Langenburg upgrades will optimize the business model, while extending performance

and capacity far beyond any conventional process.

Langenburg phase 3 retrofits

USE SYNTHESIZED FUEL TO PRODUCE HEAT FOR STEAM-POWER PRODUCTION

 

The final phase-3 involves use of the excess boiler steam from the distillation process to drive a steam-turbine for power generation.  The power unit comprises a conventional steam-turbine and Langenburg-proprietary quantum-electrodynamic generator.  Steam output from the boilers is extended by using Langenburg-proprietary nozzles and Langenburg-proprietary non-carbon fuel.  Generator output is converted to standard 60Hz alternating current  by use of a Langenburg-proprietary AC Converter.  The facility is positioned to transmit 30-50 MW of baseload power to a substation located 3/4-mile away, for transmission onto the consumer power grid.

​

visiting this facility

 

Operations at this facility have recently been available for guided tours to view progress of the phase-2 upgrades.  Invitations for tours are available to parties that have signed the Langenburg NDA with submission of a letter of interest and whom are actively pursing project-based engagement according to the Langenburg Company Policy (see guide on "proposals" menu of this website). All tours are arranged exclusively through Langenburg USA headquarters.

see also: this project in "Videos" section of this website

PROJECT LOCATION

Deployments /3

LT Spain: Shipping-Conainered Water Purification & Oxygenation System 

MORE COMING SOON

Deployments /4

LT Headquarters – Truck-Trailered Mobile Demonstrator System

COMING SOON

return-contact request

RECEIVED - RETURN CONTACT IS MADE UPON SOONEST AVAILABILITY

©2025 Langenburg Technologies, Langenburg Research, Aquarius Oxygen Spa, Aquarius Medical Spa, Langenburg Water Company – all rights reserved,

bottom of page